Works on the section at km 65+150 to 74+980 have been completed, the Warlubie junction is open in both directions.
From 4 November, the Rusocin junction will be closed in the direction of Gdańsk, which means that it will not be possible to exit the motorway in the direction of Pruszcz Gdański or enter the motorway in the direction of Gdańsk.
Work is being continued at km 50+600 to 57+300 between the Pelplin – Kopytkowo junctions, where the roadway towards Łódź will be renovated, and traffic will take place in two lanes in the direction of Gdańsk and one lane in the direction of Łódź. Renovation works on this section should be completed in the second half of November.
The speed limit on the renovated sections is 80 km/h.
Drivers are asked to increase concentration and follow the temporary traffic organization signs.
The graphics below show the temporary traffic organization on the renovated sections.
Km 0 to km 2+420 Rusocin junction
Partial closure of the gates. Traffic on the roadway in the direction of Gdańsk runs in one lane.
On November 4th from 20.00 Rusocin junction will be closed in the direction of Gdańsk.
Km 50+600 to 57+300 between Pelplin -Kopytkowo junctions:
Traffic takes place on two lanes in the direction of Gdańsk and one lane in the direction of Łódź.
For more information See where renovation works are currently being carried out