The Pelplin junction is open. Works are underway at km 17+24 in the direction of Łódź.

Works on the section at km 35+43 have been completed, the Pelplin junction is open in both directions.

In addition, works are continued on a seven-kilometre section from km 17 to km 24 located between  the Swarożyn – Stanisławie junctions, where the roadway in the direction of Łódź will be closed, and traffic will take place on the left roadway, two lanes in the direction of Gdańsk and one lane in the direction of Łódź. Works on this section should end mid August.

The speed limit on the renovated sections is 80 km/h.

Drivers are asked to increase concentration and follow the temporary traffic organization signs.

The graphic below shows the temporary traffic organization on the renovated sections.

Km 0 to km 2+420 Rusocin junction

Stage 2: partial closing of the gates. Traffic on the roadway in the direction of Gdańsk runs in one lane.

Km 50+600 to 57+300 between Pelplin -Kopytkowo junctions:

Traffic takes place on two lanes in the direction of Gdańsk and one lane in the direction of Łódź.

Km 65+150 to 74+980 between the Kopytkowo – Warlubie junctions:

The Warlubie junction is closed in the direction of Gdańsk. MOP Gajewo is closed in the direction of Gdańsk.

Traffic takes place on two lanes in the direction of Łódź and one lane in the direction of Gdańsk.

For more information See where renovation works are currently being carried out