The Pelplin junction is open. Works are underway at km 17+24 in the direction of Łódź.

Works on the section at km 35+889 to 43+350 have been completed, the Pelplin junction is open in both directions.

In addition, works are continued on a seven-kilometre section from km 17+300 to km 24+600 located between  the Swarożyn – Stanisławie junctions, where the roadway in the direction of Łódź will be closed, and traffic will take place on the left roadway, two lanes in the direction of Gdańsk and one lane in the direction of Łódź. Works on this section should end mid August.

The speed limit on the renovated sections is 80 km/h.

Drivers are asked to increase concentration and follow the temporary traffic organization signs.

The graphic below shows the temporary traffic organization on the renovated sections.

Attention Driver, rescue services exercises on A1!

On 5 December, on the A1 motorway at the level of the Kleszczewko MOP, rescue services will carry out exercises consisting in the simulation of an accident. If you notice an accident between 10.00 a.m. and 4.00 p.m. while driving past the Kleszczewko MOP, please do not call the Operator’s emergency phone number or other rescue services with information about the accident, because during these hours the Kleszczewko MOP will be the place of exercises.

In connection with the planned exercises, the following will take place:

– closing the lane in the direction of Gdańsk and redirecting traffic through the Kleszczewko MOP – parking at the Kleszczewko MOP in the direction of Gdańsk will be inaccessible to heavy goods vehicles