Completion of works on the 7-km section of the Motorway in the direction of Łódź (km 2+200 to km 9+250)

On 20 October this year, it is planned to complete renovation works on a 7-kilometre section of the Motorway in the direction of Łódź (km 2+200 to km 9+250) and to open the Kleszczewko MOP in the direction of Łódź.

Until mid-November, work will continue on a six-kilometre section of the Motorway towards Gdańsk (km 26+550 to km 20+460), where traffic runs in two lanes in the direction of Łódź and one lane in the direction of Gdańsk. In addition, vehicles heading towards Gdańsk will not be able to exit or enter at the Swarożyn junction. The completion of the works depends on weather conditions.

The speed limit on the renovated section is 80 km/h.

Drivers are asked to concentrate more closely and follow the signs of temporary traffic organization.

The graphic below shows the temporary traffic organization on the renovated section.

km 81+300 to km 90+000 between the Warlubie – Nowe Marzy junctions

Traffic will take place in two lanes in the direction of Łódź and one lane in the direction of Gdańsk.

At the Nowe Marzy junction, it will not be possible to enter the motorway either in the direction of Gdańsk or in the direction of Łódź. Vehicles driving on the motorway in the direction of Gdańsk will not be able to exit the motorway to the S5 expressway and the national road DK91. However, it will be possible to exit at the Nowe Marzy junction towards the S5 expressway (direction Bydgoszcz) for vehicles going towards Łódź.

km 35+889 to 43+350 between the Pelplin – Kopytkowo junctions

Pelplin junction closed in the direction of Łódź.

The Olsze MOP closed in the direction of Łódź.

Traffic takes place in two lanes in the direction of Gdańsk and one lane in the direction of Łódź.

 