Works in the area of the Rusocin junction from km 0 to km 2+420 have been divided into 4 stages and will last from 25 September to the end of November.
Stage 1 will consist of partial closure of the gates in the direction of Łódź. There will be 3 entry gates and 10 exit gates. This stage will last about a week.
Stage 2 is a partial closure of the gates (4 entry lanes and 8 exit lanes available) and additional surface works on a 2 km section of the roadway in the direction of Gdańsk, where traffic will run in one lane. The Rusocin interchange remains passable. The second stage will last about 2 weeks.
Stage 3 is a partial closure of the gates in the direction of Gdańsk. There will be 5 entry lanes and 8 exit lanes. The planned duration of this stage is about 2 weeks.
The last stage 4 will involve the partial closure of the gates and surface works on the roadway towards Gdańsk, where traffic will run in one lane. In addition, the Rusocin junction will be closed in the direction of Gdańsk, which means that it will not be possible to exit the motorway in the direction of Pruszcz Gdański or enter the motorway in the direction of Gdańsk at the junction. Work at this stage should start in the first week of November and be completed by the end of the month.
The speed limit on the renovated sections is 80 km/h.
Drivers are asked to increase concentration and follow the temporary traffic organization signs.
The graphics below show the temporary traffic organization on the renovated sections.