Works have been completed on the section at km 30+000 – 35+889 between the Swarożyn and Pelplin junctions. Traffic takes place in two lanes in each direction.
Work is still underway on the section at km 57+300 to 65+150 between the Kopytkowo-Warlubie junctions, where the roadway towards Gdańsk is being renovated, and traffic is moving on two lanes towards Łódź and one lane towards Gdańsk. In addition, the Kopytkowo junction in the direction of Gdańsk is closed. At the interchange, it is not possible to exit the motorway from the direction to Gdańsk onto the provincial road No. 231, or to enter the motorway in the direction of Gdańsk.
Works on this section should be completed in the second half of May.
The speed limit on the renovated section is 80 km/h.
Drivers are asked to increase concentration and follow the temporary traffic organization signs.
The graphic below shows the temporary traffic organization on the renovated section.