Work is still underway at km 65+150 to 74+980 between the Kopytkowo – Warlubie junctions. On the renovated section, traffic runs on two lanes in the direction of Łódź and one lane in the direction of Gdańsk, in addition, the Warlubie junction in the direction of Gdańsk is closed. At the interchange, it is not possible to exit the motorway in the direction of Warlubie or enter the motorway in the direction of Gdańsk. In addition, the Gajewo MOP in the direction of Gdańsk is closed. Works on this section should be completed at the end of October.
At the same time, work is being continued in the area of the Rusocin junction from km 0 to 2+420. The first stage has ended. Currently, the second stage of works is underway, which consists in the partial closure of the gates and additional surface works on a 2 km section of the roadway in the direction of Gdańsk, where traffic will run in one lane. The Rusocin interchange remains passable. The second stage will last about 2 weeks. More information about the renovation in the area of the Rusocin junction here.