Works on the section at km 65+150 to 74+980 have been completed, the Warlubie junction is open in both directions.
From 4th November, the Rusocin junction will be closed in the direction of Gdańsk, which means that it will not be possible to exit the motorway in the direction of Pruszcz Gdański or enter the motorway in the direction of Gdańsk.
Work is being continued at km 50+600 to 57+300 between the Pelplin – Kopytkowo junctions, where the roadway towards Łódź will be renovated, and traffic will take place in two lanes in the direction of Gdańsk and one lane in the direction of Łódź. Renovation works on this section should be completed in the second half of November.
The speed limit on the renovated sections is 80 km/h.
Drivers are asked to increase concentration and follow the temporary traffic organization signs.
The graphics below show the temporary traffic organization on the renovated sections.
Powiązane artykuły
From Saturday, October 26, the next stage of works in the vicinity of the Rusocin junction will […]
Works in the area of the Rusocin junction from km 0 to km 2+420 have been divided […]
From Saturday, October 26, the next stage of works in the vicinity of the Rusocin junction will […]
On 28 June, road works will begin on a seven-kilometre section from km 17+300 to km 24+600 located […]
From Saturday, 18 May 2024, on the 8-kilometre section of the Motorway towards Łódź (km 35+889 to […]
Works on the section at km 9+370 to 17+300 have been completed, and the Stanisławie junction is […]
Works on the section at km 35+43 have been completed, the Pelplin junction is open in both […]
On 26th July, works will begin at km 50+600 to 57+300 between the Pelplin – Kopytkowo junctions, […]
On 26th July, works will begin at km 50+57 between the Pelplin – Kopytkowo junctions, where the […]
Work is still underway at km 65+150 to 74+980 between the Kopytkowo – Warlubie junctions. On the […]
Works have been completed on a seven-kilometre section from km 17+300 to km 24+600 located between the […]
Work is still underway on the section at km 24+600 to 30+000 between the Swarożyn-Pelplin junctions, where […]
On 12 August, works will begin on the section at km 24+600 to 30+000 between the Swarożyn-Pelplin […]
Works on section from km 24+600 to 30+000 has ended. The Swarożyn junction is open in all […]
Works on the section at km 35+889 to 43+350 have been completed, the Pelplin junction is open […]
Work is still underway on the section at km 24+600 to 30+000 between the Swarożyn-Pelplin junctions, where […]
On 25 September, works will begin at km 0 to 2+420 at the Rusocin junction. The works […]